Jameson Avenue Reconstruction

Please be advised that starting in early August (exact date to be confirmed), Jameson Avenue will begin being reconstructed. This will include new roads and sidewalks, along with an exciting Jameson community art project which will be incorporated into the reconstruction schedule. City of Toronto construction notices will be sent out approximately one week in advance of the start date.

I wanted to provide you with as much notice as possible to prevent any surprises. The construction will involve complete closures of short segments of roadways during the watermain installation and the road reconstruction. I have been advised by City staff that driveway accesses to the apartment buildings will be maintained.

The watermain and water services reconstruction is scheduled from August to October of 2008, with the road and sidewalk reconstruction from September to November 2008. As with any other projects to be completed in November, there is always a chance that part of the final phase of the construction, depending on the weather condition, may have to be carried over to the next year. I certainly hope that will not be the case.

Should you have any questions, please email or call my office. I will keep you posted as this project moves forward.