Howard Park Construction Update

The Streetcar track renewal on Howard Park Avenue west Roncesvalles Avenue is complete, and construction crews are currently finishing some restoration work as part of Phases 1 through 5 of the project until September 27, 2020. Phase 6, the final phase of this project involves a full road closure of the intersection of Dundas Street West and Howard Park Avenue starting Monday, September 28 to October 25, 2020.

Residents/businesses who will not have access to their driveway or parking access are advised to contact Sr. Public Consultation Coordinator Paul Martin  paul.martin@toronto.ca to arrange for a temporary parking permit. Please see important parking and traffic management information related to the project in the attached Construction Update.

Online reference to Construction Update #4: https://www.toronto.ca/city-government/data-research-maps/neighbourhoods-communities/ward-profiles/ward-4-parkdale-high-park/

Howard Park Ave Track-Update